Imo Airport: Uzodimma Funds 3.2km Runway as FAAN Oversees Upgrade

0
0
Imo Airport, Cargo Airport
General Aviation Terminal at the Sam Mbakwe International Cargo Airport
Advertisement Fly Air Peace

The Imo Airport upgrade has seen the Imo State Government finance the extension of Sam Mbakwe International Airport’s runway from 2.7 kilometres to 3.2 kilometres, with the Federal Airports Authority of Nigeria (FAAN) providing institutional and technical oversight throughout the rehabilitation project.

The intervention, driven by Governor Hope Uzodimma, involved extending and resurfacing the runway, strengthening existing taxiways and improving associated aircraft movement infrastructure. FAAN, under its Managing Director, Mrs Olubunmi Kuku, played a supervisory role in coordinating the aviation authority’s technical and operational responsibilities during the project.

Advertisement

The airport, temporarily closed to allow the rehabilitation, is scheduled to reopen tomorrow, November 25, following the completion of the works and validation and approval by the Nigerian Civil Aviation Authority (NCAA).

Imo State Commissioner for Information, Public Orientation and Strategy, Hon. Declan Emelumba, announced the reopening, explaining that the intervention became necessary following the deterioration of sections of the existing 2.7-kilometre runway.

He confirmed that the Imo State Government bore the entire cost of the infrastructural upgrade.

“The rehabilitation and expansion of the Sam Mbakwe International Airport represent a significant infrastructural investment by His Excellency, Governor Hope Uzodimma,” Emelumba declared.

FAAN Supervises Imo Airport Runway Rehabilitation

While the Imo State Government provided the funding, FAAN’s role was central to the airport’s infrastructure oversight and coordination of the rehabilitation process.

Under the leadership of Managing Director, Mrs Olubunmi Kuku, the Authority provided strategic direction and institutional backing while bringing its technical and administrative capacity to bear on the project.

FAAN’s involvement extended across the different stages of the intervention, from the initial challenges and commencement of construction to the prolonged runway closure, intensive rehabilitation activities and regulatory engagements.

The Authority’s supervisory responsibilities included coordinating technical inputs, monitoring construction activities and ensuring that the rehabilitation remained aligned with aviation infrastructure and operational requirements.

The extended closure also demanded coordination between the project stakeholders and airport management to manage operational disruptions while construction activities continued.

The final validation and approval by the NCAA marked an important milestone before the airport’s scheduled reopening.

The involvement of FAAN underscores the distinction between financing an airport infrastructure project and overseeing its implementation within the operational and safety framework of the aviation sector.

500 Metres Added to Sam Mbakwe Runway

The rehabilitation has increased the runway’s length from 2,700 metres to 3,200 metres, adding 500 metres to its previous operational length.

The project also included asphalt resurfacing and strengthening of existing taxiways, addressing deterioration and improving the condition of the airport’s aircraft movement infrastructure.

These improvements are expected to enhance the airport’s operational capacity and provide additional infrastructure for aircraft movements.

The extension also creates greater runway length, although the specific aircraft categories the airport can accommodate will depend on applicable technical and operational assessments.

For FAAN, the successful completion represents an important infrastructure milestone requiring coordination between airport management, the project stakeholders and aviation regulators.

Uzodimma Targets Christmas Passenger Traffic

Emelumba explained that Governor Uzodimma anticipated increased passenger movements during the Christmas period, when many Imo indigenes and other visitors return home.

He said the governor considered it necessary to upgrade the airport ahead of the anticipated seasonal traffic to ensure smoother aircraft operations and passenger movements. Already, Air Peace has announced landmark London-Owerri flight which commences December 15, 2026, confirming that the Imo Airport will see activities at the Yuletide.

Beyond the immediate objective of improving airport operations, the commissioner described the investment as part of a broader government strategy to make Imo State more accessible to prospective investors.

He explained that improved aviation infrastructure would make it easier for business executives, investors and other visitors to access the state by air.

The upgraded Imo Airport could therefore strengthen connectivity, support commercial activities and improve access to the South-East region.

With the Imo Airport runway extension completed, associated airfield infrastructure strengthened and NCAA validation secured, the airport is preparing to resume operations.

The reopening will mark the conclusion of a demanding rehabilitation exercise financed by the Imo State Government and implemented with FAAN’s institutional and supervisory involvement under Mrs Olubunmi Kuku.