Home / Aviation News / Power supply: Pivot Engineering, partners deliver three Substations
1 x 300mVA Power Transformer & 1 x 300kVA Earthing Transformer at Alagbon 330/132/33kV GIS/AIS Substation already connected to the National Grid

Power supply: Pivot Engineering, partners deliver three Substations

In an effort to ensure reliable, quality power supply, Pivot Engineering Company Limited (PECL), a member of Honeywell Group, and its partners, including Siemens Transmission & Distribution SAS France and Siemens Nigeria Limited, have completed the power transmission projects for the upgrade of substations in Ajah, Lekki and Alagbon (Ikoyi) areas of Lagos.

Upgrading of the three substations is part of the National Integrated Power Project (NIPP) intervention of the Niger Delta Power Holding Company (NDPHC), itself an initiative of the Federal Government of Nigeria, to add significant new generation capacity to Nigeria’s electricity supply system together with associated transmission, distribution and gas supply infrastructure.

Energised 330kv GIS  Alagbon substation
Energised 330kv GIS Alagbon substation

Speaking on the project,  the General Manager Projects of Pivot Engineering, Bayo Oluwafemi said that the three substations upgraded, “are very unique and among the few GIS (Gas Insulated Switchgears) Substations embarked upon by NDPHC as majority of the other substations have AIS (Air Insulated switchgear).”

“These substations would also bring about economic benefit by strengthening the national power grid to enable the government achieve its long-term target of realizing 10,000MW”, he added.

Before the NDPHC intervention, Ajah Substation had installed capacity of 330KV 300MVA. Ajah Substation has been expanded under the NIPP initiative by the addition of 330KV 150MVA and 132KV 100MVA. The old 132KV GIS system was extended and new 330KV GIS System was installed at Ajah.

There was no Substation at Lekki before the NDPHC intervention. As a result of growth and expansion in Lekki, NDPHC contracted the Pivot-Siemens Consortium to construct the new Lekki 132/33KV 120MVA GIS Substation to also provide reliable, quality power to Lekki axis of Lagos state.

The scope of work included but was not limited to the installation of new 132KV GIS System and 33KV indoor switchgear to evacuate power though 8Nos 33KV feeders.

The Alagbon Substation was built in the 1980s and in need of repair before NDPHC commenced its upgrade. This substation feeds Ikoyi axis of Lagos state. It had 2 x 60MVA 132/33KV AIS Mobile Substation installed by TCN. However, to improve the power supply in Ikoyi, Lagos the Alagbon Substation has been upgraded by NDPHC to a 330KV substation.

Also speaking, the Director, Projects of Pivot Engineering, Robin Evans, said “the company is happy to collaborate with the Niger Delta Power Holding Company Limited in bringing its expertise and those of its partners in electrical, mechanical and civil works to bear on the power sector.”

“Nigeria needs the support of its people to maintain these public infrastructure. The power sector still faces very serious issues with buildings under high tension powerlines in urban areas, wayleave vandalising in townships and rural areas and the need for quality local labour skills”, he concluded.

 

                                                                                                               

About NigerianFlightDeck

mm
Nigerianflightdeck is an online news and magazine platform reporting business stories with a bias for aviation and travel. It is borne out of the intention to inform, educate as well as alter perceptions with balanced reportage.

Check Also

Changing face of MMIA: FAAN installs new cooling system at Arrival

Look, my brother, I have travelled this airport on numerous occasions and this is the first time in years that I step out of the aircraft and feel like I am still in a lush environment. In fact I feel the same sensation as if I’m still in the aircraft and although this is quite nice, they need to maintain it so it doesn’t get bad. Maintenance is key.”

AIB releases preliminary report of VP helicopter crash, issues two immediate safety recommendations

The initial findings also indicated that the bureau could not conduct drug and alcohol tests on the pilots and according to the weather report obtained from the Nigerian Meteorological Agency (NiMET), the prevailing conditions were good but that the aircraft hovered to land in a brown out condition.

NCAA investigates trending picture of worn out aircraft tyres, yet to establish photo veracity

"In addition to the Authority oversight roles, NCAA has placed the onerous responsibility of the first line of safety on the operating airlines’ Pilot In Command of each flight and the assigned Engineer that authorized each flight. With all the various checks and counter checks put in place by NCAA combined with that of the operators, it is therefore improbable that any airline in Nigeria will operate a service with that kind of tyre.

TSA: NAMA insists non-schedule operators must adhere to cashless payment

As part of the resolutions made at the end of the meeting, operators or their representatives are to each open and fund a domiciliary account with which to effect all financial transactions with NAMA through monetary transfers to the agency’s sub-account with the CBN using a smart phone.

Leadstream Aviation initiates plans to bring in Boeing Simulator

Tinkers strategies to save airlines operational downtime LEADSTREAM Aviation Training, recently approved as an Approved …

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this:
Skip to toolbar